Nationwide delivery available

Made to measureAll doors available in any size

Sustainable productsManufactured in the UK

Competitively pricedQuality at affordable prices

Nationwide DeliveryCompetitive shipping prices

Installation Guidance Notes for Oak Worktops

Introduction

Wood is a natural product that can be affected by heat and humidity. It can gain and lose moisture before, during and after installation. For example, wood expands when it is warm or the humidity level is high and contracts during colder periods or when the humidity level drops. When this occurs, it can cause bowing or warping. This leaflet is designed to give you all the information you require to install and care for your solid timber worktop for you to keep it in pristine condition.

We suggest you spend a short time reading through this leaflet before you start, as some recommendations are required throughout the installation process.

  • Do not discard any of the packaging until you have checked all the parts.
  • Please retain these instructions for future reference.

Storage

We recommend that all worktops are oiled immediately upon receipt and before installing your wooden worktops, we recommend applying three coats of Rustins Danish Oil to all surfaces (the end grains will require more). If you have used our pre-oiling service, you should still use Rustins Danish Oil to protect your worktops. You should oil your worktop once a week for the first six weeks, and then every three months thereafter.

Installation

Should be carried out as soon as possible after delivery. However, if storage is necessary, after oiling the worktops must be laid flat and fully supported in their original packaging. Worktops must not be placed directly onto the floor, instead separate the floor and the worktop with battens.  Battens must also be used to separate multiple worktops stored together.

Make sure the storage area is indoors, has stable humidity, and will not be subject to extremes of temperature.

DO NOT UNPACK WORKTOPS UNLESS:

  • The room humidity is stable.
  • All carcases and cabinets are built and fully fitted/complete.
  • All building dust and debris have been cleaned and cleared off-site.
  • All wet trades are finished and a sufficient period of time allowed for natural drying.
  • Fresh plasterwork has been allowed to dry for a minimum of 6 weeks or until the plaster is dry throughout.

Preparation

Before cutting your worktop, we advise oiling a small area of your worktops to ensure they all match. Before placing the worktops in situ it is important that you oil ALL the edges and faces at least twice with Danish Oil.

Wipe away any surplus oil 30 minutes after application, and allow between 6 and 8 hours between coats.

NOTE: Cut edges and areas of end grain will soak up more oil and will consequently require extra coats.

Installation precautions

When positioning the worktop you must allow a 3-4mm gap between all worktop edges and any adjacent walls or units (particularly between the back of the worktop and the wall). This will allow the worktop to expand and contract with the humidity of the kitchen without causing damage.

When a worktop is to be fitted near a freestanding oven (i.e. an oven that is not housed in a cabinet, such as a range cooker) allow a minimum gap of 30mm all the way around the worktop, and fit a solid wood end cap along the worktop edge. This will protect the end grain and help to prevent splitting.

Special care must be taken when fitting a worktop over appliances or exposed brickwork. Appliances such as dishwashers, washing machines and microwaves can produce extremes of heat and humidity. If an appliance is to be installed under the worktop, make sure a moisture barrier is used to protect the underside from any possible heat or moisture. Use the same procedure for installations when you are fixing directly onto exposed brickwork.

NOTE: The maximum unsupported overhang on any worktop is 200mm. Any larger will require additional support such as Breakfast Bar Legs to support the additional weight.

Fixing

When fixing worktops to the cabinets you must only use slotted angle brackets. A round head screw must be used to fix the bracket. It is important that you use the slot that runs perpendicular to the width (across and not parallel with the grain).

NOTE: Some cabinets are supplied with brackets that are not slotted and these must not be used. If your cabinets have a solid top or you can only secure through the cross rail you will not be able to fit slotted brackets. In these circumstances, you must drill an oversized hole (8-10mm) through the top of the carcass and secure the worktop using a larger washer and screw. This will allow the work surface to slide over the washer in case of any possible expansion or shrinkage.

IMPORTANT: Do not screw through the carcass directly into the worktop. Do not use fixing blocks to secure. Do not use any worktop fixing methods other than those recommended here.

We recommend that worktops are fitted with an upstand where necessary to cover the 4-5mm expansion gap. The upstand must be fixed to the wall and NOT the worktop. The upstand will cover the gap and hide any possible shrinkage that may occur.

NOTE: An upstand is not required where tiling or silicone will cover the expansion gap

Fixing onto masonry features

Do not fix wooden tops directly into masonry. Fit them over timber spacers 6 – 10mm thick, which are on a Damp Proof Membrane (DPM). This prevents the transmission of moisture and provides airspace under the top.

Cupped or bowed surfaces

A different installation (or in some cases re-installation) procedure is necessary should your work surface become cupped or bowed. This is unlikely but can occur as a result of incorrect/prolonged storage or moisture differences on site.

If this is the case then the following instructions apply:

  1. Fix the length of the rear of the worktop to the supporting base units.
  2. Slowly and carefully pull the worktop downwards using clamps and battens.
  3. Screw down the front edge of the worktop. Please note: it may take 1-2 weeks for the worktop to completely return to its flat shape and settle down.

Cutting & routing worktops

Where appropriate, use templates supplied with the sink/hob etc. as a guide for cutting your worktop.

IMPORTANT: Before making any cuts into your worktop ensure it is marked correctly. If drainer grooves are required they must be machined by an experienced installer/fitter. The grooves must be correctly angled towards the sink to allow any water to drain. If water does sit in the grooves, it can cause the worktop to split. When you have fitted a sink to the worktop, seal the area with an appropriate mould-resistant silicone paying special attention to the underside.

NOTE: For accuracy, quality and safety, all cutouts should be bench-cut using a jig and suitable router, never a jig saw. Having made all the cut-outs i.e. for the sink, hob etc., make sure that all cut edges are treated sufficiently and immediately with oil as previously instructed in this guidance note.

Jointing worktops

When joining two worktops together, you should use three standard worktop bolts on each joint. Seal the end grain at both sides of the joint with an appropriate sealer such as MitreSeal before making the joint. Seal the joint with sealer when the parts are finally tightened.

As a rule, only Butt joints should be used on wooden worktops. However, if your worktop has a radius and you do have to use a mitre joint, ensure that the “hockey stick” does not overextend the 10mm bull-nose radius

Sealing corner joints

Make sure any end grain has been sealed before assembling the joints.

Apply a light bead of clear low modulus silicone sealer along one side of the joint, just below the top surfaces and edges. Align the two sides with biscuits before clamping up firmly with worktop bolts. Wipe off any surplus sealant. Move the tops into place. Use thin pieces of board as temporary packing to position them with 4 – 5mm expansion gaps between the edges and ends of the tops and the walls.

Finishing worktops

You should oil your worktop once a week for the first six weeks, and then every three months thereafter.  The face of the worktop requires 4-5 coats of oil to be applied to build up a barrier against water. Allow up to 6-8 hours between coats. NOTE: Drying times will vary subject to room temperature. After fitting and before applying the final coat of oil to the face, give the worktop a light sand with fine sandpaper, remove all dust then apply the coat of oil to the surface. Spread over the entire area and allow the oil to soak in for 30 minutes, always keeping the surface covered with oil. After 30 minutes wipe off all excess to leave an even touch dry finish. Allow to dry overnight before repeating

Furniture Doors 2024 All rights reserved. Privacy Policy Cookie Policy

Marketing by Unity Online